Some news:
Our construction is stopped for 3 full weeks
It's frustrating when you have known since the beginning a continuous sequence
short, the problem is that when delivery windows, one was inadequate (problem side)
In result, initially, the plaquist we installed a board
We thought quickly the new window would be delivered, even before the plaquist completes its work
Deception , we are still waiting
Conclusion, the plaquist could not complete its work and it blocks inevitably result
soon thereafter. . . . . . .